Projects / WMATA Rosslyn Traction Power Substation Cable Tray Replacement
WMATA Rosslyn Traction Power Substation Cable Tray Replacement
Client:
Washington Metropolitan Area Transit Authority (WMATA)Owner:
Contract Value:
Caliber’s Scope:
Traction Power Systems, Communications Systems, Electrical Systems, Construction In Active Rail SystemCompletion Date:
2022
Project Scope
In conjunction with this contract to upgrade WMATA Traction Power Systems on the Red, Green, and Orange metro train lines in the Washington, DC area, C3M will install electrical equipment at five tie breaker stations and eleven traction power substations to accommodate the additional power capacity required for the 100% 8-Car Train and State of Good Repair programs. Clark Civil is part of the project and will be installing concrete pads in every location.